Fylde Council have provided further information today (Friday 9th October) as the new pools at Kirkham and St Anne;s have reached the next stage in the build programme.

Six contractors from the North West Construction Hub Framework have said they want to bid for both schemes.

Fylde Council say they are picking a contractor in two stages:

Stage 1: By November, they will choose one or two preferred lead contractors.

Stage 2: The chosen contractor will work with the Council early on. They’ll help shape the build programme, advise on the best way to build, and firm up costs. This means the final contract will be realistic and deliverable.

Lytham St Anne’s News will keep you updated as things progress.